Project Start Date: Tue 1/11/00
Project Finish Date: Tue 4/18/00
ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
---|---|---|---|---|---|---|
1 | Schedule and Outline Delivery | 0 days | Tue 1/25/00 | Tue 1/25/00 | ||
2 | Final Group Project Poster | 0 days | Tue 4/18/00 | Tue 4/18/00 | ||
3 | Final Oral Group Presentation | 0 days | Tue 4/18/00 | Tue 4/18/00 | 2 | |
4 | Data Acquisition | 1.75 days | Tue 1/25/00 | Wed 1/26/00 | ||
5 | Acquire various house data | 0.25 days | Tue 1/25/00 | Tue 1/25/00 | Kevin Riley | |
6 | Determine most suitable from data sources | 0.25 days | Tue 1/25/00 | Tue 1/25/00 | 5 | Kevin Riley |
7 | Acquire regional data (RMOC) | 0.25 days | Tue 1/25/00 | Tue 1/25/00 | 6 | Kevin Riley |
8 | Acquire Lakes.shp for backdrop | 0.25 days | Wed 1/26/00 | Wed 1/26/00 | 7 | Kevin Riley |
9 | Analyze data properties, capabilities | 0.5 days | Wed 1/26/00 | Wed 1/26/00 | 8 | Kevin Riley |
10 | Data Integration | 7 days | Wed 1/26/00 | Fri 2/4/00 | 4 | |
11 | Establish metadata standard for housing data | 0.5 days | Wed 1/26/00 | Thu 1/27/00 | Tom Kralidis | |
12 | Format house data to metadata standard (XML) | 2 days | Thu 1/27/00 | Mon 1/31/00 | 11 | Tom Kralidis |
13 | Assign topology to region selection / input layers (ArcView) | 3 days | Mon 1/31/00 | Thu 2/3/00 | 12 | Kevin Riley |
14 | Geocode house data against street network data (ArcView) | 1 day | Thu 2/3/00 | Fri 2/4/00 | 13 | Kevin Riley |
15 | Develop operational tools for automated data conversion (C, Perl) | 0.5 days | Fri 2/4/00 | Fri 2/4/00 | 14 | Tom Kralidis |
16 | Application Development | 42 days | Mon 2/7/00 | Tue 4/4/00 | 10FS-1 day | |
17 | Research other housing / real estate GUIs | 0.5 days | Mon 2/7/00 | Mon 2/7/00 | Kevin Riley | |
18 | Determine most desired data access mechanisms, GUIs | 1 day | Mon 2/7/00 | Tue 2/8/00 | 17 | Kevin Riley |
19 | Develop framework / standard / dataflow | 1 day | Tue 2/8/00 | Wed 2/9/00 | 18 | Tom Kralidis |
20 | Avenue Development | 39.5 days | Wed 2/9/00 | Tue 4/4/00 | 19 | |
21 | Query data / bitmaps, develop search mechanism (ArcView / Avenue) | 15 days | Wed 2/9/00 | Wed 3/1/00 | Tom Kralidis | |
22 | Interim Project Evaluation 1 - Data Acquisition, Formatting, Input complete | 0 days | Wed 3/1/00 | Wed 3/1/00 | 21 | |
23 | Develop data extraction / export methods (ArcView / Avenue) | 7 days | Wed 3/1/00 | Fri 3/10/00 | 22 | Tom Kralidis |
24 | Program networks, grid data (ArcView / Avenue) | 17.5 days | Fri 3/10/00 | Tue 4/4/00 | 23 | Tom Kralidis[35%],Kevin Riley[50%] |
25 | ActiveX / MapObjects Development | 8 days | Tue 4/4/00 | Fri 4/14/00 | 20 | |
26 | Research feasibility, protability, web access tools | 2 days | Wed 4/5/00 | Thu 4/6/00 | Kevin Riley | |
27 | Interim Project Evaluation 2 - Avenue Development Completed | 0 days | Tue 4/4/00 | Tue 4/4/00 | ||
28 | Develop basline application using GEOHome principles (VB, MapObjects) | 8 days | Wed 4/5/00 | Fri 4/14/00 | Tom Kralidis[50%] | |
29 | Output / Display | 7 days | Wed 4/5/00 | Thu 4/13/00 | 16 | |
30 | Investigate portability between platforms, environments | 2 days | Wed 4/5/00 | Thu 4/6/00 | Tom Kralidis[15%] | |
31 | Develop final data flowchart | 1 day | Fri 4/7/00 | Fri 4/7/00 | 30 | Kevin Riley |
32 | Make recommendations to alternative / non GIS solutions | 1 day | Mon 4/10/00 | Mon 4/10/00 | 31 | Kevin Riley |
33 | Write technical documentation | 2 days | Tue 4/11/00 | Wed 4/12/00 | 32 | Tom Kralidis[50%] |
34 | Develop project poster | 1 day | Thu 4/13/00 | Thu 4/13/00 | 33 | Kevin Riley |
35 | Prepare laptop / presentation media items | 1 day | Mon 4/10/00 | Mon 4/10/00 | Tom Kralidis[25%] | |
36 | Group Oral Presentation | 0 days | Tue 2/29/00 | Tue 2/29/00 | ||
37 | Final Group Assessment | 0 days | Tue 4/18/00 | Tue 4/18/00 | 3 |