methodology_targetDates


Project Start Date: Tue 1/11/00
Project Finish Date: Tue 4/11/00

Task_Data

IDTask_NameDurationStart_DateFinish_DatePredecessorsResource_Names
1
Schedule and Outline Delivery
0 daysTue 1/25/00Tue 1/25/00  
2
Final Group Project Poster
0 daysTue 4/11/00Tue 4/11/00  
3
Final Oral Group Presentation
0 daysTue 4/11/00Tue 4/11/00  
4
Data Acquisition
1.75 daysTue 1/25/00Wed 1/26/00  
5
Acquire various house data
0.25 daysTue 1/25/00Tue 1/25/00 Kevin Riley
6
Determine most suitable from data sources
0.25 daysTue 1/25/00Tue 1/25/005Kevin Riley
7
Acquire regional data (RMOC)
0.25 daysTue 1/25/00Tue 1/25/006Kevin Riley
8
Acquire Lakes.shp for backdrop
0.25 daysWed 1/26/00Wed 1/26/007Kevin Riley
9
Analyze data properties, capabilities
0.5 daysWed 1/26/00Wed 1/26/008Kevin Riley
10
Data Integration
7 daysWed 1/26/00Fri 2/4/004 
11
Establish metadata standard for housing data
0.5 daysWed 1/26/00Thu 1/27/00 Tom Kralidis
12
Format house data to metadata standard (XML)
2 daysThu 1/27/00Mon 1/31/0011Tom Kralidis
13
Assign topology to region selection / input layers (ArcView)
3 daysMon 1/31/00Thu 2/3/0012Kevin Riley
14
Geocode house data against street network data (ArcView)
1 dayThu 2/3/00Fri 2/4/0013Kevin Riley
15
Develop operational tools for automated data conversion (C, Perl)
0.5 daysFri 2/4/00Fri 2/4/0014Tom Kralidis
16
Application Development
31.5 daysMon 2/7/00Tue 3/21/0010FS-1 day 
17
Research other housing / real estate GUIs
0.5 daysMon 2/7/00Mon 2/7/00 Kevin Riley
18
Determine most desired data access mechanisms, GUIs
1 dayMon 2/7/00Tue 2/8/0017Kevin Riley
19
Develop framework / standard / dataflow
1 dayTue 2/8/00Wed 2/9/0018Tom Kralidis
20
Avenue Development
29 daysWed 2/9/00Tue 3/21/0019 
21
Query data / bitmaps, develop search mechanism (ArcView / Avenue)
15 daysWed 2/9/00Wed 3/1/00 Tom Kralidis
22
Interim Project Evaluation 1 - Data Acquisition, Formatting, Input complete
0 daysWed 3/1/00Wed 3/1/0021 
23
Develop data extraction / export methods (ArcView / Avenue)
7 daysWed 3/1/00Fri 3/10/0022Tom Kralidis
24
Program networks, grid data (ArcView / Avenue)
7 daysFri 3/10/00Tue 3/21/0023Tom Kralidis[35%]
25
ActiveX / MapObjects Development
8 daysTue 3/21/00Fri 3/31/0020 
26
Research feasibility, protability, web access tools
4 daysTue 3/21/00Mon 3/27/00 Kevin Riley
27
Interim Project Evaluation 2 - Avenue Development Completed
0 daysTue 3/21/00Tue 3/21/00  
28
Develop basline application using GEOHome principles (VB, MapObjects)
8 daysTue 3/21/00Fri 3/31/00 Tom Kralidis[50%]
29
Output / Display
15.5 daysTue 3/21/00Tue 4/11/0016 
30
Investigate portability between platforms, environments
3.33 daysTue 3/21/00Fri 3/24/00 Tom Kralidis[15%]
31
Develop final data flowchart
5 daysFri 3/24/00Fri 3/31/0030Tom Kralidis[20%]
32
Make recommendations to alternative / non GIS solutions
1 dayFri 3/31/00Mon 4/3/0031Tom Kralidis
33
Write technical documentation
1 dayMon 4/3/00Tue 4/4/0032Tom Kralidis
34
Develop project poster
2 daysTue 4/4/00Thu 4/6/0033Kevin Riley
35
Prepare laptop / presentation media items
2 daysMon 4/10/00Tue 4/11/00 Tom Kralidis[25%]
36
Group Oral Presentation
0 daysTue 2/29/00Tue 2/29/00  
37
Final Group Assessment
0 daysTue 4/11/00Tue 4/11/003