methodology_targetDates


Project Start Date: Tue 1/11/00
Project Finish Date: Tue 4/11/00

Task_Data

IDTask_NameDurationStart_DateFinish_DatePredecessorsResource_Names
1
Schedule and Outline Delivery
0 daysTue 1/25/00Tue 1/25/00  
2
Final Group Project Poster
0 daysTue 4/11/00Tue 4/11/00  
3
Final Oral Group Presentation
0 daysTue 4/11/00Tue 4/11/00  
4
Data Acquisition
1.75 daysTue 1/25/00Wed 1/26/00  
5
Acquire various house data
0.25 daysTue 1/25/00Tue 1/25/00 Kevin Riley
6
Determine most suitable from data sources
0.25 daysTue 1/25/00Tue 1/25/005Kevin Riley
7
Acquire regional data (RMOC)
0.25 daysTue 1/25/00Tue 1/25/006Kevin Riley
8
Acquire Lakes.shp for backdrop
0.25 daysWed 1/26/00Wed 1/26/007Kevin Riley
9
Analyze data properties, capabilities
0.5 daysWed 1/26/00Wed 1/26/008Kevin Riley
10
Data Integration
7 daysWed 1/26/00Fri 2/4/004 
11
Establish metadata standard for housing data
0.5 daysWed 1/26/00Thu 1/27/00 Tom Kralidis
12
Format house data to metadata standard (XML)
2 daysThu 1/27/00Mon 1/31/0011Tom Kralidis
13
Assign topology to region selection / input layers (ArcView)
3 daysMon 1/31/00Thu 2/3/0012Kevin Riley
14
Geocode house data against street network data (ArcView)
1 dayThu 2/3/00Fri 2/4/0013Kevin Riley
15
Develop operational tools for automated data conversion (C, Perl)
0.5 daysFri 2/4/00Fri 2/4/0014Tom Kralidis
16
Application Development
20 daysMon 2/7/00Fri 3/3/0010FS-1 day 
17
Research other housing / real estate GUIs
0.5 daysMon 2/7/00Mon 2/7/00 Kevin Riley
18
Determine most desired data access mechanisms, GUIs
1 dayMon 2/7/00Tue 2/8/0017Kevin Riley
19
Develop framework / standard / dataflow
1 dayTue 2/8/00Wed 2/9/0018Tom Kralidis
20
Avenue Development
17 daysThu 2/10/00Fri 3/3/0019 
21
Query data / bitmaps, develop search mechanism (ArcView / Avenue)
4 daysThu 2/10/00Tue 2/15/00 Tom Kralidis
22
Interim Project Evaluation 1 - Data Acquisition, Formatting, Input complete
0 daysTue 2/15/00Tue 2/15/0021 
23
Develop data extraction / export methods (ArcView / Avenue)
7 daysWed 2/16/00Thu 2/24/0022Tom Kralidis
24
Program networks, grid data (ArcView / Avenue)
6 daysFri 2/25/00Fri 3/3/0023Tom Kralidis
25
ActiveX / MapObjects Development
12 daysMon 3/6/00Tue 3/21/0020 
26
Research feasibility, protability, web access tools
4 daysMon 3/6/00Thu 3/9/00 Kevin Riley
27
Interim Project Evaluation 2 - Avenue Development Completed
0 daysTue 3/14/00Tue 3/14/00  
28
Develop basline application using GEOHome principles (VB, MapObjects)
4 daysThu 3/16/00Tue 3/21/00 Tom Kralidis
29
Output / Display
26 daysMon 3/6/00Mon 4/10/0016 
30
Investigate portability between platforms, environments
2 daysMon 3/6/00Tue 3/7/00 Tom Kralidis[50%]
31
Develop final data flowchart
1 dayWed 3/8/00Wed 3/8/0030Tom Kralidis
32
Make recommendations to alternative / non GIS solutions
1 dayThu 3/9/00Thu 3/9/0031Tom Kralidis
33
Write technical documentation
3 daysFri 3/10/00Tue 3/14/0032Tom Kralidis
34
Develop project poster
2 daysWed 3/15/00Thu 3/16/0033Kevin Riley
35
Prepare laptop / presentation media items
1 dayMon 4/10/00Mon 4/10/00 Tom Kralidis[50%]
36
Group Oral Presentation
0 daysTue 2/29/00Tue 2/29/00  
37
Final Group Assessment
0 daysTue 4/11/00Tue 4/11/003